Project Timeline

Environment Impact Assessment Screening
Public Consultation

Undertaken in mid 2021.

Submission of Planning Application

The application was submitted to Central Bedfordshire Council and can be viewed HERE.

Assessment and Determination of Planning Application

The application was accepted in May 2022.

Construction

Planned to commence in quarter 2 of 2023.

55%
Active

Project Overview

Tebworth Solar Farm would provide renewable electricity for distribution to the National Grid via the substation at Sundon. This project will generate energy each year of the proposed 40 years of operational life, while also providing a substantial carbon dioxide savings when compared to generation of electricity by non-renewable sources.

The proposals include battery storage which will allow energy to be stored on site at times when grid-demand is lower and exported at times of higher demand to ensure no energy is ‘lost’ and help balance the National Grid. 

Comprising approximately 62 hectares of land, there are no statutory landscape, heritage or ecological designations on site, as part of our site surveys and further assessments we will be considering these matters carefully in developing our proposals for consultation. 

The development forms a temporary (40 year) use of farmland that is easily reversed at the end of the operational life. A scheme of landscape and ecological improvements will be prepared to support the application, ensuring the project provides a biodiversity net gain.

Access will be from the A5 and take approximately 6 months.