Project Timeline

Environment Impact Assessment Screening
Public Consultation

Statutory publicity and consultation Pre-Application Consultation 1st November 2023 to 13th December 2023.

Submission to PEDW

Submitted April 2024

Examination by the PEDW

This is to take place under the DNS system is expected during 2024.

Construction

Expected to commence in 2025.

18%
Active

Project Overview

As the development capacity will be more than 10MW, it is defined as a Development of National Significance (DNS). This means that the planning application will be submitted to the Planning and Environment Decisions Wales (PEDW) and considered by an Inspector with the final decision made by Welsh Ministers.

Alaw Môn would provide renewable electricity for distribution to the National Grid. This project would generate a significant amount of energy each year of the proposed 40 years of operational life, while also providing a substantial carbon dioxide savings when compared to generation of electricity by non-renewable sources. The proposals include battery storage which will allow energy to be stored on site at times when grid-demand is lower and exported at times of higher demand to ensure no energy is ‘lost’ and help balance the National Grid. 

Our Alaw Môn project has a separate website, www.alaw-mon-solar-farm.co.uk , which hosts all documents.